Separate hours from monetary cost
Keep project-coded hours alongside the rate basis used to cost them. A planning rate and a payroll rate answer different questions. Label which one appears in each report, who owns it and when it changed. Managers can review hours without seeing individual pay rates.
Reconcile one project-week
In a fictional installation project, 80 approved hours at a planning rate of 30 give a labor estimate of 2,400. A labor budget of 3,000 leaves 600 headroom on the same basis. Record the period and currency. If 12 hours are pending approval, show them separately so the apparent headroom is not mistaken for a final saving.
Give each variance an owner
Sort differences into additional hours, rate changes and coding errors. Ask the project lead to confirm time and finance to confirm the cost basis. Keep revenue, subcontractor invoices and non-labor expenses in separate inputs before estimating total margin.